Our vision is to complete the single piece flow by incorporating inspection and wash and pack into the cell as depicted in this future state Standard Work sheet. The question is, "Will those tasks impact the existing cycle time to manufacture?"
How could we use the tools to find out ?
Small Turning Cell
We are still moving the parts 668' to final inspect them and 311' to wash and pack them.
This is the resultant Standard Work that was written after creating single piece flow for just the machining part of the process.